Description of Activity:
This activity includes the test and examination of samples by using reliable test tools and checking manufacturing date, storage condition and checking its compliance of quality standards and technical specification provided by UNDP to suppliers: Sehab Tech 1500W – Al-Wahbani 1000W.

Output
Inputs
-     Report of sample test results.

Defined places of sample test with the coordination of suppliers. The test process was tackled by the consultant engineer of Adawr Organization for the systems (1000W-1500W) in different places; in the stores of Sehab Tech, Al-wahabani and finally in the premises of Reyada Corporation. Where the systems installed and operated for 3 days by suppliers then examined by engineers testing effectiveness in accordance with the centrally defined standards and specifications.



Note:
-       The specified period of the central sample test which was decided in the plan as one day was exceeded however it took 10 days; this is because some equipment of 1000 W of the supplier Al-Wahbani did not match the standards and specifications that were agreed centrally. Where it was stipulated on (Al-Wahbani) by the engineer to change some equipment such as batteries and inverters that we re changed accordingly. However, the engineers in Adawr suggested installing and operating 1000W system in the premises of Reyada NGO for 3 days to do test and examination procedures and to agree on them after testing.

-       Test and examination of 1500W system of the supplier Sehab Tech, it was matching with the standards agreed centrally. 